Document duration-based Continuum runtime estimates
This commit is contained in:
@@ -112,6 +112,27 @@ count at two and increases `chunk_seconds` from 6 through 10. The bypass
|
||||
counterparts use the same settings. This shows whether longer individual
|
||||
clips are viable before combining them into 30-second projects.
|
||||
|
||||
## Runtime planning
|
||||
|
||||
The latest observed reference is **18 minutes for one 4-second chunk**. Until
|
||||
more measurements are available, the monitoring estimate is:
|
||||
|
||||
`expected minutes = 18 × (total generated seconds ÷ 4) + 5-minute buffer`
|
||||
|
||||
Examples:
|
||||
|
||||
| Generated duration | Estimated render | Monitoring window |
|
||||
|---:|---:|---:|
|
||||
| 4s | 18m | 23m |
|
||||
| 5s | 22.5m | 28m |
|
||||
| 8s | 36m | 41m |
|
||||
| 20s | 90m | 95m |
|
||||
| 30s | 135m | 140m |
|
||||
|
||||
These are planning windows, not performance guarantees. Each completed test
|
||||
must replace its estimate with the measured runtime and the model should be
|
||||
recalibrated if multi-clip scaling is not approximately linear.
|
||||
|
||||
The bypass series uses the identical seed, references, prompt text, model,
|
||||
samplers, scheduler, upscale settings, tile geometry, and chunk plan. Only the
|
||||
Spectrum path changes. Results should be compared in pairs: CT-01 vs CT-B01,
|
||||
|
||||